Tue, 16th Feb 2021 14:29:00 |
EuroTrough Helped Cut Ramp-Up Time of China’s 100 MW Urat CSP |
The 100 MW Urat CSP first connected to the grid in January of 2020, with 3 months of commissioning, and by December, met its full production target within just one year, according to CSNP. Typically, thermal plants require up to four years to ramp-up to 100% operating level.
At Urat, the solar collector field covers an area 2.6 km long and 1.7 km wide. It consists of 352 loops comprising 16,896 individual solar collector elements, each 12 m long and 5.8 m wide. The firm’s existing EuroTrough design was originally developed for 50 MW plant sizes, and has been successfully used in many trough power plants in Spain, Egypt, India, Kuwait and previously in China. But Urat presented challenges.
“It would have been uneconomical to just copy the design for the 100 MW Urat CSP plant, as extremely high wind loads, the influence of high altitude on air pressure, and a wide temperature range, from -45 °C in winter to over 30 °C in summer, made re-engineering necessary,” said Axel Schweitzer, sbp solar engineer.
Read original full article
|
Atlantis Viewpoint
|
|
|
|
Back to Featured Articles
|
|
|
|
|
|
|
|
|
|
|
Energy News
|
|
|
|